This past Sunday Kevin Duda recorded his first Hole in One on the 12th hole. The person he bumped out of the parking spot - Rob Connors just happened to witness the shot while he was getting ready to tee off on the 13th Tee.
The passing of the parking spot was a civilized transaction with only a large amount of kidding involved!
Congratulations Gents!
Friday, August 30, 2013
Monday, August 26, 2013
Construction update
Progress on our new practice facility was moving right on
schedule………….until we received an inch of rain this morning……….and at this
point the rain continues to fall. Companies that move and shape dirt for a
living are use to weather challenges, and knowing we might get hit with rain
they had implemented some proactive measures to reduce the delays rain might
cause. It’s a little early for me to say for certain, but I would anticipate
losing today to weather, but expect the construction to commence tomorrow. It
won’t take them long to make up a days work. The normal schedule for our
construction crew is to work 12 hour days, taking weekends off. If production
is lost due to weather, weekends will be used to get our project back on
schedule. By the end of this week we will be able to see things taking shape.
We will be able to see where the new road is roughed in, what area the parking
will take up, and where the new range tee is located. I can’t stress enough how
dangerous it is for anyone to walk into the work area with all the heavy
equipment running around. The blind spots for the drivers on this heavy
equipment are huge, and with the dust blowing around it is easy to have
incredibly poor visibility. Please do not, at any time enter the construction
zone.
The aerification of our six sand greens was completed
successfully. These areas were also over seeded at the same time. Thank you to
members who have been so patient and understanding as we mow and water these
greens in the afternoon in and around play. If you don’t recall, we mow
aerified greens in the afternoon when they are dry as we pick up a lot less
sand. In the morning the wet turf makes the sand sticky causing a big mess,
duller blades and slower recovery.
Watering in mid afternoon keep the turf canopy cool and gives life giving
moisture to all the new seedlings.
This week you will see the enlarged portions of the greens
on 9, 13, 14 and 15 have the sod and the organic mat layer
r emoved. These areas will then have new root zone installed
and they will be prep’d for sod installation which is scheduled to happen on
Tuesday September 4th. Each of these areas will be marked G.U.R.
probably for the duration of the 2013 season. The reason the areas will be
striped of sod this week, but not sodded until next week is simply because of
the time it takes to complete the task. Remembering we still need to maintain
the golf course, and we have already lost staff who have returned to school, we
need the full week to get all these areas stripped and properly prepared for
the sod which will all be cut, transported and installed in one day by another
crew.
Some members have questioned why we don’t just allow the Poa
to take over on these greens as it seems to be performing better than the bent
stand. Under the low oxygen conditions we have been experiencing Poa actually
stands up to that better than bent. Simply put, we will always have a blended
stand of both Poa and bent on our greens. The only way to eliminate one over
the other would be to undertake a complete reconstruction program such as the
one Donalda club is currently going through. This would encompass complete
excavation of all green cavities removing the root zone right down to the sub
grade and rebuilding them from there. And, after r e-establishing
the turf, many extra chemical applications and hand picking the Poa out on a
regular basis would be required. We have been removing Poa plants manually on
the 12th green (but not the collar) and even I was surprised at the
extra man power required to stay on
top of the program. Attempting this on 18 greens would be monumental and a very
costly venture. Once we get our aerification program on track we will all see
healthier bent grass.
Wednesday, August 21, 2013
PRO SHOP SALE
It is our last few weeks in the Pro Shop so we have everything on Sale!!
Mens Wear - 40 % off
Women's Wear - 40 to 60 % off
Rainwear and Outerwear - 30% off
Accessories - 20% off
Shoes - 25% off
Wedges and Putters - 25% off
Demo Clubs are on Sale Now!
* Sale applies to all in stock merchandise - does not apply to Special Orders.
Mens Wear - 40 % off
Women's Wear - 40 to 60 % off
Rainwear and Outerwear - 30% off
Accessories - 20% off
Shoes - 25% off
Wedges and Putters - 25% off
Demo Clubs are on Sale Now!
* Sale applies to all in stock merchandise - does not apply to Special Orders.
Tuesday, August 20, 2013
Long Drive Champ - Niilo Schonfeld
Our own Niilo Schonfeld has qualified and will be competing in the Canadian and World Long Drive Championships this fall.
Niilo will be showcasing his talent for each group Wednesday afternoon on the first tee from 12 to 5pm.
Any or all contributions in support of Nillo's quest to be a world champion will be greatly appreciated.
Niilo will be showcasing his talent for each group Wednesday afternoon on the first tee from 12 to 5pm.
Any or all contributions in support of Nillo's quest to be a world champion will be greatly appreciated.
Friday, August 16, 2013
Great Construction Shots
Thanks to member Norm Ullock who sent over some great pictures of the range construction. Currently the top soil is being stripped and stockpiled for use later on. The big push may happen within the next two weeks. On Monday August 18th the asphalt on the upper and lower parking will be ground up and stockpiled on the entrance road just east of the 17th tee. Members will need to veer right at this point to access the parking. We encourage all members to carpool when possible as parking will limited. The clubhouse patio and washrooms will be open until the temporary trailers are fully up and running, we hope this is within a week.
Tuesday, August 13, 2013
IT BEGINS..............................
So there's no need to tell you we are in a "Go for full throttle" position on our practice facility. The fill permit is now in hand so the practice facility and the parking lot construction can move full steam ahead. Silt fence will be completed before the end of this week. And the stripping and stock piling of top soil has begun. Once all top soil has been stock piled and saved outside of the actual construction zone the major earthworks begin. Currently the northern most parking lot is the highest point of land we have. This area, along with our current (or former) tee deck will drop in elevation just over a full meter. When the entire R2R process is finished, the new clubhouse will be on the highest point of land which promises to be a spectacular site. For the many member who have been with us for 8 or less years you probably have no idea of what Whitevale Golf Club was like before the 2004/2005 renovation.
Here we are in the spring of 2004 looking down the same site line on 4 as the previous picture. For most member this may seem alien. The huge oak tree between 4 and 5 is there, you just can't see it from all the cedars all the way down the left side. You could almost just about run and jump over the pond. I think everyone would agree that what we have is a huge improvement over what we had. But, keep in mind it took a while to go from one......to the other.
Here's what we had mid construction. Lots of dirt, heavy equipment, and a closed golf course. And this is exactly what we are going to have on our practice facility and clubhouse for at least a year. There will be dirt. There will be dust. There will be parking shortages..........and the list goes on. If we all accept what the short term pains and inconveniences will be, and keep an optimistic and positive attitude, we will all be happier and this will be relatively painless................and in a year from now we can post what the range and clubhouse USED to look like. So from here we go hammer down, pedal to the metal, full speed ahead, full after burner...................well...........................you get the picture.
Wednesday, August 7, 2013
Club Championship 2013
The 2013 Club Championship was held this past week with qualifiers competing on Championship Monday. A few familiar faces were again crowned Club Champs. Congratulations to Mark Brewer and Angela Colm - your 2013 Champions.
The weekend had some beautiful, almost fall like weather. Strong breezes made conditions interesting for the Sunday and Monday rounds especially since they were out of the north on Sunday and the south on Monday!
A special "Thank You" to all those who volunteered their time over the weekend to assist with the Pace of Play. The juniors helped as Spotter for any errant shots and the Timers let groups know how they were doing time wise. The result - a great pace of play all weekend.
Congratulations to everyone who played this weekend!
The weekend had some beautiful, almost fall like weather. Strong breezes made conditions interesting for the Sunday and Monday rounds especially since they were out of the north on Sunday and the south on Monday!
A special "Thank You" to all those who volunteered their time over the weekend to assist with the Pace of Play. The juniors helped as Spotter for any errant shots and the Timers let groups know how they were doing time wise. The result - a great pace of play all weekend.
Congratulations to everyone who played this weekend!
2013 Club Championship Results | |||
Men | Score | ||
Championship Flight | |||
1st | Mark Brewer | 294 | |
2nd | Alex Letros | 299 | |
2nd | Mark Burrell | 299 | |
4th | Niilo Schonfeld | 317 | |
A Flight | |||
1st Gross | Jim Glover | 240 | |
2nd Gross | Heinz Dahn | 249 | |
1st Net | Ed Griffin | 215 | |
2nd Net | Paul Lacour | 220 | |
B Flight | |||
1st Gross | John Liska | 263 | |
2nd Gross | John Jumas | 266 | |
1st Net | Don Hobb | 217 | |
2nd Net | Ryan Robillard | 223 | |
C Flight | |||
1st Gross | Neil Downs | 266 | |
2nd Gross | Ryan Chong | 277 | |
1st Net | Tom Kelly | 210 | |
2nd Net | Ken Fedosen | 215 | |
Weekday Men's | |||
1st Gross | Sasha Mikijeli | 258 | |
2nd Gross | Tom O'Connor | 266 | |
1st Net | Frank Winter | 213 | |
2nd Net | Ted Addie | 269 | |
Women | Score | ||
Championship Flight | |||
Champ | Angela Colm | 251 | |
2nd Gross | Jacquelyn Dunne | 255 | |
3rd Gross | Ann Griffin | 268 | |
B Flight | |||
1st Gross | Barb Rogers | 282 | |
1st Net | Debbie Couch | 225 | |
C Flight | |||
1st Gross | Joan Store | 311 | |
1st Net | Kandice Brackenbury | 232 | |
Junior Champion | |||
Brenden Dunphy | 251 | ||
Juvenile | |||
1st Gross | James Daigle | 267 | |
1st Net | Andrew Rogers | 235 | |
Bantam | |||
1st Gross | Eamonn O'Neill | 315 | |
1st Net | Matt Billington | 212 | |
Girls | |||
1st Gross | Lauren Bevan | 276 | |
1st Net | Kaprice Brackenbury | 219 | |
Friday, August 2, 2013
Club Championship - Live Scoring
To view Championship scoring go to : www.golfscoring.net/whitevale
Scores will begin to be posted after 11:30 each day.
Don't forget to join the crowd on Monday and cheer on the Champions as they finish at the 18th!
Free BBQ - so bring your family and friends to celebrate this great Annual Event.
Scores will begin to be posted after 11:30 each day.
Don't forget to join the crowd on Monday and cheer on the Champions as they finish at the 18th!
Free BBQ - so bring your family and friends to celebrate this great Annual Event.
Subscribe to:
Posts (Atom)